Speed ​​up the progress of important transport infrastructure projects

The Government has never spent as much resources on key infrastructure development as in the past time. In addition to the medium-term public investment capital 2021-2025, the National Assembly recently also agreed to spend about 114 trillion VND in the economic recovery package 350,000 billion VND for infrastructure development.

A series of policies have been more liberal in order to accelerate the implementation of important infrastructure projects, demonstrating the urgency and expectation of soon having projects that contribute to economic growth for the country.

Efforts to ensure progress

Peak dry season, all construction packages under the project North-South expressway Phase 1 is accelerating. Up to this point, out of 10 component projects under construction, there are 8 basic projects that meet the schedule.

“The enterprise mobilizes the maximum amount of machinery, divided into 3 segments, each segment is a commander and continues to be divided into construction points,” said Mr. Nguyen Manh Tuong – Xuan Truong Co., Ltd.

Mr. Nguyen Luong Cong – Son Hai Group Co., Ltd. said: “The company has focused its total efforts on working 3 shifts, 4 crews, on the construction site there is always an explosion 24/24h”.

Speeding up the progress of important transport infrastructure projects - Photo 1.

A series of policies have been more liberal to speed up the implementation of important infrastructure projects. Illustration – Photo: VNA.

Currently, many project management boards of the North-South expressway project phase 1 have set a basic goal of completing 3 months before, that is, in September this year many sections will be put into operation.

Mr. Luong Van Long – Project Management Director of Mai Son – National Highway 45 said: “It is not because of progress that we ignore quality. When the contractor overtime increases, relevant departments such as consultants. supervision, the Project Management Board must also increase personnel and increase the time to follow the construction site.

Right this year, there will be 4 component projects under the North – South expressway project phase 1 including: section Mai Son – National Highway 45, Cam Lo – La Son, Vinh Hao – Phan Thiet and Phan Thiet – Dau Giay was completed and put into operation.

Removing obstacles for key traffic projects

The Ministry of Transport also confirmed that this year the ministry will complete 26 key transport projects. These are projects with inter-regional connectivity, not only soon forming a modern transportation system, but also contributing to boosting the economy of many localities and regions.

In order to continue to improve the infrastructure system, this year the Prime Minister assigned a public investment plan to the Ministry of Transport with a total budget of more than VND 50,000 billion. This is the largest delivery plan ever, accounting for nearly 10% of the country’s 2022 capital plan.

However, in order to timely disburse this important capital source, breakthrough policies are still needed to remove obstacles from site clearance to price increases and lack of material supply in many bidding packages. part of the North-South expressway project.

Speeding up the progress of important transport infrastructure projects - Photo 2.

The Ministry of Transport confirmed that this year the ministry will complete 26 key transport projects. Illustration – Photo: Dan Tri.

The Government has issued 2 Resolutions 60 and 133 to speed up the process of granting land mines for the North-South expressway project phase 1. However, at the local level, the shortcomings have not been resolved. The risk of delay in many bidding packages of the North-South expressway project phase 1 is increasingly present.

Not only is there a shortage of land to fill the road, many construction units are also facing difficulties when the price of raw materials increases abnormally.

“The price fluctuates daily, so there are orders and suppliers that have been canceled after negotiation,” said Mr. Hoang Dinh Thinh – Deo Ca Group Joint Stock Company.

The leader of the Ministry of Transport affirmed: All projects in both phases of the North-South expressway must meet the schedule to ensure a modern transport system for economic development. .

“The implementation of phase 2 to connect with phase 1 and some sections we have completed, forming an expressway from north to south. It demonstrates regional connectivity, linking all regions Northern coastal and mountainous provinces, with the Mekong Delta provinces. From this axis, a continuous traffic network will be formed, in order to exploit the country’s potential and strengths”, said Mr. Nguyen Van The – Minister of Transport transport said.

Along with phase 1 and phase 2 of the North-South expressway project, the remaining 729 km with a total investment of about 147 billion VND are also being urgently deployed. According to the plan, the project will be completed in the period of 2025 – 2026.

Recently, the Ministry of Transport held consultations with leading enterprises in the field of transport to continue implementing phase 2 of the North – South expressway project. According to analysts, this is a step that shows the great determination of transportation industry to realize the Government’s direction on investment in building transport infrastructure for economic development in the current period.

* Invite readers to watch programs broadcast by Vietnam Television on TV Online and VTVGo!

You are reading the article Speed ​​up the progress of important transport infrastructure projects
at Blogtuan.info – Source: vtv.vn – Read the original article here

Back to top button