Vinh Hao – Phan Thiet Expressway is behind schedule

Binh ThuanThe Vinh Hao – Phan Thiet toll road project is more than 100 km long, delayed due to weak contractor management apparatus.

This information has just been released by Project Management Board 7 (Ministry of Transportation), the investor section of the Vinh Hao – Phan Thiet report to the Department of Construction Management and Traffic Quality on the progress of the toll road.

According to Project Management Board 7, as of mid-March, the construction and installation value of the entire project was more than VND 1,750 billion, accounting for nearly 29% of the contract value, almost 10% behind the plan.2,360 billion VND).

Since the beginning of the year until now, the construction progress in this section has changed slowly, the realized output is only 403 billion VND, reaching more than 37% of the plan, not meeting the requirements in items, especially embankments.





The Vinh Hao - Phan Thiet expressway project is still widespread in the section through Ham Chinh commune, Ham Thuan Bac district (Binh Thuan), March 2022. English: Viet Quoc

Vinh Hao – Phan Thiet expressway project in Ham Chinh commune, Ham Thuan Bac district (Binh Thuan) in mid-March. Vietnamese

This project was delayed because the contractor had not been able to proactively procure soil materials, and road embankment work was still slow in all bid packages, only reaching 76% of the plan. Some contractors have not been drastic, did not pay enough attention to the importance of the project.

Investors assessed that the contractor management apparatus was lacking in number, weak in capacity, not authorized to operate the construction team and subcontractors. This leads to unscientific construction organization and uncoordinated construction and installation. Machinery and equipment on the construction site are not maximizing their capacity.

In addition, project financing is short, sources of money at construction sites are delayed, affecting the mobilization of supplies, materials and fuel. Construction points across the route also only mobilize 80/86 compared to the need. At present, 4 project bid packages have more than 2,400 employees and nearly 1,300 machines and equipment.

According to Project Management Board 7, if contractors don’t change the way they do things, they won’t follow the schedule and it will be difficult to complete the volumes on contract. At a recent meeting to review progress with the Ministry of Transportation, the contractors committed to deploy all resources to complete the project according to the established schedule.

If the contractor continues to violate commitments, the contractor will be fined 0.05% of the contract value for each day of violation but not more than 12% of the contract value; The pending volume will be truncated to another unit to perform…

Yesterday, Deputy Transport Minister Nguyen Ngoc Dong held a meeting with the People’s Committee of Binh Thuan province to discuss solutions to eliminate some of the difficulties in construction materials for this expressway.





Vinh Hao - Phan Thiet expressway directions.  Image: Thanh Huyen

Vinh Hao – Phan Thiet expressway directions. graphic: rod suspension

The North-South Highway passes through Binh Thuan province with a total length of more than 160 km, including three component projects: Cam Lam – Vinh Hao, Vinh Hao – Phan Thiet and Phan Thiet – Dau Giay.

In it, paragraph Vinh Hao – Phan Thiet longest, with 6 lanes, 32 m wide; The total investment capital of almost 11,000 billion VND, started in November 2020, is expected to be completed this year.