Deputy Prime Minister: Don’t let any losses or negatives happen at Long Thanh Airport Project

Deputy Prime Minister Le Van Thanh.

The quality of the Long Thanh airport project must come first

Project Long Thanh International Airport has a large scale, is very important for socio-economic development, security – defense; When completed, it will create a strong driving force for the development of Dong Nai, the provinces of the Southern Key Economic Zone and the whole country.

Given the importance of the Project, the Prime Minister decided to establish a Government Steering Committee to direct the implementation; The Steering Committee must achieve the following basic objectives: The project progress must be completed by 2025 in accordance with the National Assembly’s Resolution and the Prime Minister’s Decision; The quality of the Project must be put first, commensurate with the scale of being an important national work, with high requirements on quality, architectural design and landscape; Against negative waste; save investment costs.

Deputy Prime Minister Le Van Thanh, Head of the Steering Committee highly appreciated the members of the Steering Committee, the People’s Committee of Dong Nai province, the Airports Corporation of Vietnam (ACV) and the contractors for their efforts, achieving the results. positive results in the last 2 months: The site clearance work has handed over an additional 328.59 hectares in the construction area of ​​phase 1 and 332.28 hectares in the land reserve area; ACV’s Project Management Unit has been consolidated with full functions, legal status, human resources and facilities enhanced; Contractors have mobilized a lot of equipment and machinery, mobilized human resources to work in 3 shifts, the atmosphere on the construction site was initially vibrant…

In order to implement the Project to meet the progress and quality, the Head of the Steering Committee asked the members of the Steering Committee, the Ministry of Transport, the People’s Committee of Dong Nai Province and relevant ministries and branches to continue to try and focus on maximum in the work of direction and administration, absolutely no loss, waste, negativity.

The Steering Committee is responsible for reviewing and urging the implementation progress, investment procedures to ensure timely, quality control; maintaining monthly briefings in accordance with the Operational Regulations with specific and detailed contents.

The investors closely coordinate with local forces (defence, police) to ensure absolute security and order during the construction process.

The Ministry of Transport, the Ministry of Construction and members of the Steering Committee organized field trips, grasped the situation, encouraged officials and employees on the construction site, and proposed to the Head of the Steering Committee according to the field of management. .

By April 30, 100% of the land area will be handed over to phase 1

Dong Nai Provincial People’s Committee mobilizes the participation of the whole political system in site clearance work, well implements propaganda and mobilizes people to comply with compensation and resettlement guidelines and policies. ground delivery. The Chairman of the Provincial People’s Committee directly inspects and handles difficulties and problems at the scene, directs the application of policies, arranges temporary residence, supports… according to his/her competence, ensuring the target by 15/15. 4 reached 80%, by April 30, 100% of the land area will be handed over to phase 1; in June 2022 handing over the entire area of ​​5,000 ha.

For the Component 1 project, the Ministry of Public Security, the Ministry of Finance, the Ministry of Transport and the People’s Committee of Dong Nai province are required to proactively and expeditiously prepare and implement investment in housing management agencies’ headquarters. water at airports (Customs, Public Security, Border Gate Police, Port Authority, Health Quarantine) in accordance with the law, ensuring synchronous completion by the end of 2024.

With Project Component 2, Vietnam Air Traffic Management Corporation urgently deploys survey and design work (completed in June 2022) to carry out the next works, ensuring construction completion. construction and equipment supply by the end of 2024.

For Project component 3 (including the most important work items of the Project):

+ ACV continues to perfect the operation regulations of the Project Management Board, perfect the personnel apparatus, add more working areas for experts, supervision consultants,…

+ ACV actively cooperates with the Ministry of Transport and the Ministry of Construction to ensure the design approval schedule of the passenger terminal in July 2022 and start construction in October 2022; Start of the runway in December 2022.

As for the Component 4 Project, the Ministry of Transport is responsible for organizing the implementation of the works, ensuring the completion progress, and synchronous testing with the project’s component projects.

Timely guide and promulgate prices of fuel and raw materials

Regarding the price of construction materials, the Ministry of Construction, the Ministry of Finance and the People’s Committee of Dong Nai province promptly guide and promulgate prices of fuel and raw materials according to their competence and according to regulations.

The calculation of traffic demand connecting Long Thanh International Airport should be based on a long-term vision when fully exploiting the capacity of 100 million passengers/year. The Ministry of Transport will soon study and expand the route freeway Ho Chi Minh City – Long Thanh – Dau Giay, along with roads under construction (Ben Luc – Long Thanh Expressway, Ring Road 3 of Ho Chi Minh City) ensure to meet traffic demand. connection, no congestion occurs.

The Ministry of Transport and the People’s Committee of Dong Nai province agreed to invest in traffic routes connecting the airport (DT.773 and DT.770B) to ensure large enough scale, limiting investment in upgrading, later expansion.

Regarding the railway lines connecting Long Thanh Airport, the Ministry of Transport, Dong Nai Provincial People’s Committee and relevant agencies implement the direction of the Deputy Prime Minister in Document No. 1941/VPCP-CN dated March 30. 2022, report to the Prime Minister the most optimal plan to speed up the investment implementation.

* Invite readers to watch programs broadcast by Vietnam Television on TV Online and VTVGo!

You are reading the article Deputy Prime Minister: Don’t let any losses or negatives happen at Long Thanh Airport Project
at Blogtuan.info – Source: vtv.vn – Read the original article here

Back to top button