On the morning of April 26, Dang Thuc Vinh road (Provincial Road 9, Hoc Mon district) that caused many inconveniences to people was officially opened after nearly 4 years of construction.

The project of repairing and upgrading the road officially started on October 10, 2018, there were 1,188 cases of affected houses so they had to be cleared.

During the construction process, there was no synchronization between the contractors, so the construction was sluggish, greatly affecting the people’s daily life. In particular, people here have complained about the road causing dust when it is sunny, and muddy when it rains during construction.

Ho Chi Minh City: Traffic on the route is nearly 700 billion after 4 years of repair and upgrade - Photo 1.
Ho Chi Minh City: Traffic on the route is nearly 700 billion after 4 years of repair and upgrade - Photo 2.
Ho Chi Minh City: Road traffic is nearly 700 billion after 4 years of repair and upgrade - Photo 3.

Dang Thuc Vinh Street is designed with 4 lanes for motor vehicles

In addition, after completing the reconstruction of the road surface, the line of electric poles “growing” in the middle of the road is still slow to move, causing danger to vehicles.

After nearly 4 years of weariness, people in this area have just settled down when the road connecting Binh Duong province with Cu Chi, Hoc Mon and Long An provinces is open to traffic.

The project is invested with the goal of contributing to regional traffic connection in the direction of Provincial Road 9, improving traffic capacity, contributing to reducing flooding, improving the environment, embellishing urban beauty. , stabilize people’s lives in the area and gradually improve the traffic infrastructure system according to the planning, contributing to promoting the economic development of Hoc Mon district in particular and the surrounding areas of the city in general.

Ho Chi Minh City: Road traffic is nearly 700 billion after 4 years of repair and upgrade - Photo 4.
Ho Chi Minh City: Traffic on the route is nearly 700 billion after 4 years of repair and upgrade - Photo 5.
Ho Chi Minh City: Traffic on the route nearly 700 billion after 4 years of repair and upgrade - Photo 6.

After completing the upgrade and repair of this arterial road, it will connect traffic in the Northwest of Ho Chi Minh City with Binh Duong and Long An provinces.

The project of upgrading and repairing with items such as building a drainage system along the sidewalk and across the road, outlet at the locations of drainage canals ensures drainage for the area and for the road.

Planting trees, building a lighting system along the route suitable to the landscape and complete according to road level; to build a complete road signaling system to ensure traffic safety, suitable to the size of the road.

The total investment of this project is 698 billion VND, of which 465 billion VND is for construction work.

At the opening ceremony, Mr. Vo Van Hoan – Vice Chairman of Ho Chi Minh City People’s Committee said that the completion of the project on the occasion of April 30 and May 1 was a great joy for Ho Chi Minh City.

“The completed project helps to perfect the infrastructure system, connect regional traffic and reduce traffic accidents, overcome congestion, flooding and improve the environment, urban embellishment, and quality improvement. quality of people’s lives,” Mr. Hoan said.

https://kenh14.vn/tphcm-thong-xe-tuyen-duong-gan-700-ty-sau-4-nam-sua-chua-nang-cap-20220426110115773.chn


According to the Four Quarters

You are reading the article Clearing the road nearly 700 billion after 4 years of repairing and upgrading
at Blogtuan.info – Source: cafebiz.vn – Read the original article here

Back to top button