Đời sống

Cement factory project of VND 5,000 billion “died prematurely” after 15 years of aggressive construction

07/05/2022 08:46 GMT+7

The creepy cold scene in the abandoned buildings of the 5000 billion project makes anyone who goes in also falter. The project was expected but died prematurely after 15 years

Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly derelict
Phu Son cement factory project in Phu Son commune (Ngo Quan district, Ninh Binh) was started construction in 2007, on an area of ​​more than 40 hectares, total investment of 5,000 billion VND, is expected to come into operation next year. 2011 with a capacity of about 11 million tons/year.
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly derelict
Up to now, 15 years have passed, the project is still “covering mats”, stopping construction for many years.
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly derelict
As noted by PV, in the project site, only the unfinished operating and working house, 2 floors, staff housing area, wall, rockery, completed leveling…
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly derelict
The rockery is surrounded by overgrown weeds.

Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate

The new cadre housing area has only a set of rooms, after many years of being abandoned, it causes a creepy feeling when coming here.
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
The wall surrounding the abandoned project looks like it’s been hundreds of years
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
Inside the site where the executive building is built
Cement factory project of VND 5,000 billion “died prematurely” after 15 years of aggressive construction
The yard on the 2nd floor of the house, the water cannot drain, forming a puddle like a pond
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
The 2nd floor area of ​​the house is mossy and moldy, imprinted with time even though it’s just a frame set up
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
Before the construction of the cement project, this area was the agricultural land of 2 rice people (the rice bowl of Ninh Binh province – PV) with about 200 affected households.
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
After the people gave up their land for the project, 60 local children were allowed to go to cement vocational training in Hai Phong with the promise that they would return to work at the factory, but so far there is no factory, these people had to find work. other for a living.
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
Inside the abandoned operator’s house, people use it to raise pigeons or keep cows…
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly derelict
Over time, the items deteriorated, this place made a place for cattle to live.
Hundreds of households give up their land for a 5,000 billion cement factory, 15 years later, the scene is terrifyingly desolate
Unfinished deep holes in the cement factory project’s premises turned into trap pits.

On September 11, 2017, the People’s Committee of Ninh Binh province agreed to terminate the operation of the Phu Son cement plant construction investment project. In addition, the Provincial People’s Committee also assigned the Management Board of Industrial Parks to assume the prime responsibility for, and coordinate with the Departments of Justice, Planning and Investment, Finance, Construction, Industry and Trade, Natural Resources and Environment, Nho Quan District People’s Committee and relevant departments. related to implementing procedures for project termination, revocation of investment certificates, land recovery…

After that, Phu Son Cement Joint Stock Company (the Company) sent a document to the People’s Committee of Ninh Binh province, departments, and branches stating the reason for financial difficulties leading to the stagnation in the implementation of activities. factory building for a long time. The company also pledged to start the construction of the factory from November 20, 2017, but so far it has remained “immovable”.

Tran Nghi

You are reading the article Cement factory project of VND 5,000 billion “died prematurely” after 15 years of aggressive construction