At the press conference on the socio-economic situation in April 2022 organized by the People’s Committee of Binh Duong province recently, the representative of the Department of Natural Resources and Environment (TN&MT) of Binh Duong province informed about the violations of the Company. CP C-Holdings at Phu Tho Quoc Cuong Apartment project.

Phu Tho Quoc Cuong Apartment Project (trade name is C-River View), located at Phu Tho Ward, Thu Dau Mot City, Binh Duong Province. This is a project invested by C-Holdings Joint Stock Company.

The legal representative and General Director of this company is Mr. Nguyen Quoc Cuong, also known as Cuong “dollar”.

loat sai pham tai tieng cua cong ty cuong do la tai du an c river view 84ea8b042d0a4c71a68685d048608681
The C-River View project has many violations of land, environment and construction.

According to Mr. Dinh Hoang Bao – Deputy Head of the Department of Planning and Land Registration under the Department of Natural Resources and Environment of Binh Duong province, in the process of C-Holdings Joint Stock Company implementing the C-River View project, this investor has made many mistakes related to related to land and environment.

About landC-Holdings Joint Stock Company received the transfer of land use rights of 5,607.4m2 (the land for the implementation of the C-River View project) from individuals but did not register changes according to regulations.

In addition, the investor of the C-River View project also has the act of organizing the construction of works on land planted with perennial crops and non-agricultural production facilities.

In the field of environment, C-Holdings Joint Stock Company has constructed the foundation of the project without being approved by the competent authority. environmental impact assessment report.

With the above violations, the People’s Committee of Binh Duong province has issued decisions sanction administrative violations for C-Holdings Joint Stock Company, the total amount of this business fined is more than 600 million VND.

Not only violations in the field of land and environment, the investor of the C-River View project was also twice administratively sanctioned for illegal construction of the project.

As VietNamNet Le Huu Nhon – Chief Inspector of Binh Duong Department of Construction has twice issued a decision to sanction administrative violations against C-Holdings Joint Stock Company for illegal construction at the project. C-River View project.

Specifically, the first sanctioning decision was signed on February 9, 2021. At that time, C-Holdings Joint Stock Company was fined 40 million VND for constructing the underground part. Violating construction items include: Pressing 361 mass piles, 79 bored piles and 5 experimental piles.

The Inspector of the Department of Construction requested that, within 60 days from the date of making a record of administrative violations (ie before April 5, 2021), the investor must carry out procedures to request a competent authority to issue a permit. construction permit.

loat sai pham tai tieng cua cong ty cuong do la tai du an c river view c758c9ac8d524206bf15da6f7fa87e32
As for illegal construction, the investor of the C-River View project has been fined twice.

However, the investor of the C-River View project not only did not comply with the above sanctioning decision, but also continued to execute the project without permission.

The decision to sanction C-Holdings Joint Stock Company for illegal construction for the second time was signed by Chief Inspector of Binh Duong Department of Construction on January 10, 2022. At this time, the investor has constructed a series of items with a total violation construction area of ​​more than 11,700m2.

With the recidivism of illegal project construction, C-Holdings Joint Stock Company was fined with aggravation. The second fine is VND 50 million.

Talk to PV VietNamNeta leader of Binh Duong Department of Construction once said that allowing C-Holdings Company to re-offend construction without permission was due to the loose management of the Inspector of the Department of Construction and the responsibility of the head belonged to Chief Inspector Le. Huu Nhon.

According to this person, Binh Duong Department of Construction has implemented discipline Mr. Le Huu Nhon with the form of review and experience.

After many scandalous mistakes, according to research, the C-River View project has now been granted a construction permit.

Mr. Phuong

You are reading the article A series of scandalous mistakes of Cuong ‘dollars’ at the C-River View project
at Blogtuan.info – Source: vietnamnet.vn – Read the original article here