Unit 1 of Thai Binh 2 thermal power plant successfully connected to the national grid

This is an important milestone of the project, affirming the political determination and efforts to overcome difficulties of the Vietnam Oil and Gas Group, the collective Thai Binh 2 PMU, the General Contractor PETROCONs and related contractors in completing the project. completed, put the plant into operation and commercial electricity generation on schedule.

Thai Binh 2 Thermal Power Plant Project is a national key project that receives the attention and close and regular direction of the Government, Ministries/ Departments/ Sectors and leaders of the Group, with the desire to put the project into operation. commercial by the end of this year.

The completion of important milestones of the first oil burning of Unit 1 on February 23, 2022 and today the milestone of oil synchronizing Unit 1 into the national power grid is a testament to the “revival of Unit 1″. ” of project.

Up to now, the overall progress of Thai Binh 2 Thermal Power Plant Construction Project has reached more than 93%; design achieved 99.9%, procurement completed about 97.32%; about 40% of the trial run is completed; construction and installation work was completed about 93.88%.

In order to achieve the above milestones, the Vietnam Oil and Gas Group, the PMU, the General Contractor/subcontractors have highly focused and mobilized all resources to accelerate the construction, installation and test-run progress. Experience with Thai Binh 2 Thermal Power Plant Project, and at the same time implement many synchronous solutions to solve the project’s difficulties.

The Vietnam Oil and Gas Group organized to strengthen the project management apparatus, mobilized hundreds of officials, engineers and workers from units in the oil and gas industry to participate in supporting the project in product preparation. production, repair, maintenance, commissioning. Currently, there are always about 1,000-1200 construction engineers and workers directly involved in the project.

Before that, on May 8, 2022, Prime Minister Pham Minh Chinh and the Government’s delegation came to inspect and work at the project. Speaking at the meeting, the Prime Minister praised and highly appreciated the efforts, efforts and responsibilities of workers on the construction site, shared some lessons, and continued to review and adjust the organize work to ensure thrift, efficiency and safety.

With the constant attention and direction of the Government, the determination of the Vietnam Oil and Gas Group, the Project Management Board, the General Contractor of PetroCons/subcontractors and the collective of workers on the construction site, the Vietnam Oil and Gas Group believes believe that the project will finish on schedule.

You are reading the article Unit 1 of Thai Binh 2 thermal power plant successfully connected to the national grid