Thai Binh 2 thermal power project ‘revived’

The Thai Binh 2 thermal power project that once caused the Vietnam Oil and Gas Group to have a headache has officially “revived” when generating the power of unit 1 running oil on the national grid.

On the afternoon of May 13, at Thai Binh 2 Thermal Power Plant, the Vietnam Oil and Gas Group (Petrovietnam) held a ceremony to connect to the power grid of Unit 1, marking the first time the project generated electricity on the national grid. .

hon 10 nam lao dao du an 2 ty usd hoi sinh c2574e59ce7c46a6ac75e4876ed7197a
Thai Binh 2 thermal power project used to face many difficulties

Petrovietnam Chairman of the Board of Directors Hoang Quoc Vuong said that this is an important milestone to move towards the next milestones and put the plant into commercial operation in 2022. After connecting to the power grid of Unit 1, the block The amount of work is very large, it is requested that the PMU and the general contractor continue to closely coordinate to continue promoting the spirit of creative labor and responsibility to put the unit into coal-fired power generation.

“Experiencing a long time of difficulties due to epidemics, interruption of supplies, disruption of the supply chain of raw materials and especially the mobilization of human resources from foreign contractors… To overcome this difficulty, The project management board, general contractor and sub-contractors have closely coordinated and emulated production labor to complete the milestones,” noted Petrovietnam’s Chairman.

Up to now, the overall progress of Thai Binh 2 Thermal Power Plant Construction Project has reached more than 93%; design achieved 99.9%, procurement completed about 97.32%; about 40% of the trial run is completed; construction and installation work was completed about 93.88%.

During the implementation process, the Project encountered many difficulties, stalled due to subjective and objective reasons, even at times fell into a stalemate, there were many opinions that it was necessary to put “urgently”. “The project is on the list of weak projects in the Industry and Trade sector.

On May 8, 2022, Prime Minister Pham Minh Chinh and the Government’s delegation came to inspect and work at the project. Speaking at the meeting, the Prime Minister praised and highly appreciated the efforts, efforts and responsibilities of workers on the construction site, shared some lessons, and continued to review and adjust the organize work to ensure thrift, efficiency and safety.

hon 10 nam lao dao du an 2 ty usd hoi sinh 525967eeb13649a7b0dce30a93eecc30
The project has passed the most difficult period. Photo: Luong Bang

Previously, with the goal of completing Thai Binh 2 Thermal Power Plant with quality assurance on schedule by the end of 2022, within 6 months, Deputy Prime Minister Le Van Thanh went directly to the construction site 4 times, directing, hot handling of each problem, mechanism, policy, creating trust and above all, timely encouraging employees at the Project.

At the request of the Deputy Prime Minister, every week, Petrovietnam sends an update report on the implementation and construction situation at the Project to promptly grasp the situation and handle possible difficulties and problems. affect progress. It is the attention and companionship of the Government, the Prime Minister and directly Deputy Prime Minister Le Van Thanh that has created the motivation and confidence for the leaders and employees of Petrovietnam to strengthen their determination and high efforts. create a strong change, step by step put the project into motion quickly.

“The construction site must be crowded with people, there must be a lively, enthusiastic atmosphere, unanimously agreeing to solve common problems. Only then can we overcome difficulties and deal with existing problems of the project”, that is the spirit that Deputy Prime Minister Le Van Thanh always emphasizes during his visits to and works at the Project.

Luong Bang

hon 10 nam lao dao du an 2 ty usd hoi sinh b08b6c7949484f2088e9489a371dd114

Mobilizing hundreds of good engineers to revive the Thai Binh 2 Thermal Power Project

In just 8 months, Government leaders 4 times came down to directly inspect the progress of Thai Binh 2 Thermal Power Project, remove difficulties and immediately handle obstacles to speed up progress and generate electricity on 30/30. 4.

You are reading the article Thai Binh 2 thermal power project ‘revived’
at Blogtuan.info – Source: vietnamnet.vn – Read the original article here