A series of mistakes at the Hap Linh housing project, Bac Ninh city

Inspectors of Bac Ninh province have just concluded the inspection of the housing project in Hap Linh ward, Bac Ninh city, which pointed out many violations.

According to the conclusion, the Hap Linh housing project has a total investment of more than 53.1 billion VND, built on an area of ​​65,145m2, of which the residential land area is 19,247m2. The investor of the project is the People’s Committee of Bac Ninh City. The unit that won the auction of land use rights and invested in the construction of technical infrastructure was Duc Phat Kinh Bac Joint Stock Company.

During the implementation process, the project still had errors in land acquisition, planning and approval, compensation payment, site clearance support and land handover.

A series of mistakes at the Hap Linh housing project, Bac Ninh city - 1

The housing project in Hap Linh ward, Bac Ninh city still exists, the Inspector of Bac Ninh province asked Duc Phat Kinh Bac Joint Stock Company to only transfer and raise capital when it is eligible and allowed. (Photo: HH)

Specifically, the investor, the People’s Committee of Bac Ninh City, assigned the City Construction Project Management Board to prepare compensation and support plans for site clearance, but this agency did not have the function and task of organizing the project. carry out site clearance.

Bac Ninh City People’s Committee, Bac Ninh City Compensation and Site Clearance Council, Bac Ninh City Construction Project Management Board and Hap Linh Ward People’s Committee made mistakes in preparing and approving urban wastewater support funds. Government regulations on compensation, support and resettlement when the State recovers land. On the other hand, the funding to support urban wastewater is not regulated by the decision of the People’s Committee of Bac Ninh Province and has not been approved by the Chairman of the Provincial People’s Committee.

The compensation and site clearance council of Bac Ninh city, the construction project management board of Bac Ninh city and the People’s Committee of Hap Linh ward did not prepare a compensation plan to support the relocation of the 110kV power line running through the project. But making a plan and paying 30% support for representatives of the Women’s Union and Farmers’ Union with an amount of more than 180 million VND is not the right target.

Propaganda and mobilization of households to receive compensation and support for site clearance to implement the project of Bac Ninh City Compensation and Clearance Council, Bac Ninh City Construction Project Management Board and People’s Committee Hap Linh ward has not been effective, leading to the application of coercion to 10 households and individuals (to date, households have not received compensation and support money).

In organizing the auction of land use rights, the Bac Ninh Provincial Property Auction Service Center does not conduct field inspections for the auctioned land according to regulations. Currently, within the project boundary, there is still a power line and a 110kV high voltage pole running through the project and has not been moved.

On the side of the auction winning unit, Duc Phat Kinh Bac Joint Stock Company, was late in paying land use fees to the state budget and was charged a late payment fee of more than VND 8.4 billion. Not only that, during the inspection, this enterprise provided incomplete records and documents of the stage of construction investment implementation.

The enterprise has not yet prepared an additional dossier for the housing part, which must be built with the rough part and completed on the outside, and submitted to the competent authority for approval according to regulations; The construction procedures and documents have not been completed yet to organize the implementation of the investment project approved by the Provincial People’s Committee.

Although not yet qualified to start construction as prescribed, they still leveled a part of the project area (about 30%) and constructed the foundation of the main road, from outside the national highway 38 to make roads in and out. project.

Regarding the transfer of land use rights, at the time of inspection, Duc Phat Kinh Bac had not been granted a land use right certificate and had not been confirmed by the state management agency to be eligible for land use right transfer. .

Clarifying individual and collective wrongdoing

According to the inspection agency, the People’s Committee of Bac Ninh City is responsible for approving the project plan that partially overlaps the power grid safety corridor of the 110kV power line.

The People’s Committee of Bac Ninh City is also responsible when assigning the City Construction Project Management Board to make a plan for compensation and support for site clearance that is not in accordance with regulations.

Bac Ninh City People’s Committee, Bac Ninh City Compensation and Site Clearance Council, Bac Ninh City Construction Project Management Board and Hap Linh Ward People’s Committee are responsible for making and approving funding to support urban wastewater. regulations; failing to make a plan for compensation and support for shifting the 110kV power line running through the project; making plans and paying 30% of support funds to the wrong subjects…

The asset auction service center of Bac Ninh province is also responsible for not conducting field inspections of the auctioned land according to regulations.

Meanwhile, Duc Phat Kinh Bac Joint Stock Company is responsible for late payment of land use fees to the state budget; have not yet prepared an additional dossier for the part of the house that must be built with the rough part and completed the exterior and submitted to the competent authority for approval according to regulations; complete construction procedures and documents to organize the implementation of investment projects approved by the Provincial People’s Committee; conduct ground leveling of part of the project’s area when the conditions are not met to start the work as prescribed…

Since then, the Provincial Inspectorate requested the People’s Committee of Bac Ninh City, the Compensation Council for Site Clearance of Bac Ninh City, the City Construction Project Management Board and the People’s Committee of Hap Linh Ward to organize a review of collectives and individuals. related to the shortcomings and violations in the implementation of the above-mentioned projects, according to their competence.

Request the Bac Ninh Property Auction Service Center to organize a review of the groups and individuals involved in the existence and mistakes in not conducting field inspections of the auctioned land. according to the law.