Reporting to the 15th National Assembly, the 3rd session, the Government said: 17 agencies have not yet disbursed public investment capital in 2022. It will clarify objective and subjective reasons and responsibilities of each level. each branch in the delay in capital disbursement, report to the National Assembly.

17 agencies have not yet disbursed public investment capital

The report said that the state budget capital (State budget) in 2022 is estimated to be paid by April 30, 2022 at 95,724.49 billion VND, reaching 18.48% of the plan assigned by the Prime Minister, approximately the same period in 2021 (the same period in 2021, reaching 18.65% of the plan). plan assigned by the Prime Minister).

In which: domestic capital is 94,592.89 billion VND, reaching 19.57% of the plan assigned by the Prime Minister; foreign capital is 1,131.61 billion VND, reaching 3.25% of the plan and 17 ministries and central agencies have not yet disbursed the capital plan.0

17 agencies have not yet disbursed public investment capital in 2022: Clarifying the cause,

17 ministries and central agencies have not yet disbursed public investment capital plans in 2022. (Photo: TN)

Citing reports of ministries and central agencies on the reasons for not disbursing the capital plan, the Minister mentioned a number of reasons.

For new start-up projects: After being assigned the capital plan, the new investor implements procedures such as approving the contractor selection plan, to the step of making, appraising and approving the technical design. , design construction drawings, select construction contractors, provide equipment for items corresponding to the assigned capital plan value. Normally, the time to prepare these procedures is about 6 months, so the disbursement will start from the second quarter of 2022.

For transitional projects: the contract has been advanced since the end of 2021, until now the contractors are implementing construction, the first months of 2022 have not yet come to the payment period according to the contract to the contractor, so the disbursement has not been disbursed. .

In addition, a number of projects have problems with site clearance, especially land counting to compensate and support people.

According to the report, on May 2, 2022, the Prime Minister issued Decision No. 548/QD-TTg establishing 6 working groups led by 04 Deputy Prime Minister and Minister of Planning and Investment, The Minister of Finance shall act as the team leader to inspect, urge, remove difficulties and obstacles, and accelerate the disbursement of public investment capital in 2022 at ministries, central agencies and localities until April 30. allocating all assigned public investment capital plans in 2022; the disbursement rate as of April 30 was below the national average (18.48%).

The Working Groups will specify objective and subjective reasons and responsibilities of each level and sector for the delay in capital disbursement. The Minister shall report to the National Assembly.

17 agencies have not yet disbursed public investment capital in 2022: Clarifying the cause,

Minister Nguyen Chi Dung: Will specify objective and subjective reasons and responsibilities of each level and sector for the delay in capital disbursement and report to the National Assembly. (Photo: VPQH)

AsianThe pressure to disburse capital in 2022 is huge

Minister Nguyen Chi Dung informed that the state budget investment plan in 2022 decided by the National Assembly in Resolution No. 34/2021/QH15 is VND 526,105,895 billion.

Besides this capital, it is necessary to disburse a large amount of capital from 60-80 trillion VND of the Socio-Economic Development and Recovery Program.

Therefore, the pressure to disburse capital in 2022 is very large, requiring the participation and efforts of all levels and sectors from the central to local levels.

In which, the role of heads of ministries, central and local agencies must be enhanced.

Heads of ministries, central and local agencies must play a good role in promulgating decisions to lead, direct, and administer effectively the key tasks and breakthroughs. proactively and actively in leading and directing the promulgation of many solutions to promote disbursement of public investment capital, proactively removing difficulties and obstacles related to land and natural resources; reviewing and regulating change capital investment plans between projects that are slow to be disbursed to projects with good disbursement progress, need additional capital, etc. to be accountable for the disbursement results as well as the investment efficiency of projects assigned to manage,” the report stated.

In the direction and key tasks, the Government’s report also clearly states: Implement quickly, synchronously, drastically and more effectively the tasks and solutions set out in Resolution No. 43/2022/ QH15 of the National Assembly and Resolution No. 11/NQ-CP of the Government; focus on drastically implementing solutions to promote disbursement of public investment in 2022. At the same time, identifying these as key political tasks and one of the important criteria for final evaluation and classification. years for organizations and individuals, especially the head.