Being reminded many times, the project of more than trillions in Da Nang “accelerated” construction

On May 25, Mr. Nguyen Minh Huy – Director of Danang Traffic Construction Investment Project Management Board (Construction Investment Project Management Board), the investor of the western ring road project in Da Nang, said that the project is underway. require contractors to strengthen parallel construction points to strive for June 30 to open the public service route of the western ring road project of Da Nang.

This is a slow-moving project, which has been pointed out by many violations by the Da Nang inspector and reminded many times by Da Nang’s leaders.

“Recently, the Board has worked with CIENCO 1 contractor to request to terminate the delayed construction subcontractor contract in the past time and replace a new contractor to work and work overtime at night”, Mr. Huy said.

Being reminded many times, the project of more than 1,000 billion VND in Da Nang

The overpass category of National Highway 14B belongs to the ring road project west of Da Nang. Photo: DB

According to Mr. Huy, currently, the old contractor has pulled the machine out of the construction site and the new contractor is bringing the machine to approach and deploy the project items under the direction of the investor.

As noted by PV, in the past few days, taking advantage of the strong sunny weather, the Danang Traffic Construction Investment Project Management Board directed contractors to mobilize manpower and machinery to speed up the leveling and construction of the ring road project. west of the city.

In the bidding package of Traffic Construction Company 1 (Cienco 1), section Km 0 – Km 2+100, the contractor speeded up the leveling of the last K95 ground layer, prepared to fill K98, ready to cover with grade stone. distribute. Compared to half a month ago, the construction site has improved a lot, the road surface is basically covered with earth, vehicles can travel easily.

Being reminded many times, the project of more than 1,000 billion VND in Da Nang

Contractors strengthen parallel construction points to strive for June 30 to open the public service route of the western ring road project of Da Nang. Photo: DB

Mr. Hoang Nguyen Son, official of Da Nang Traffic Construction Investment Project Management Board (managing the Cienco 1 package), said that at the beginning of the route, the K95 embankment has been basically completed, especially the section Km 2+600 – Km 4 has been completed. 50%. The abutment of the QL14B overpass is being covered with the first layer of coarse sand, both doing and testing the technology.

In terms of leveling, Mr. Son said, on average every day, the Cienco 1 package transports and fills more than 3,000 m3 of soil and 1,000 m3 of sand to treat soft soil. With the current progress, by June 30, 2022, the route will be opened under the direction of leaders of Da Nang City.

Mr. Son added, currently, it is difficult to transport the leveling land to fill the front line. Specifically, the leveled land must be transported from Km 6 to the beginning of the route, but the current public service route is only enough for 1 lane due to some uncleared documents. The contractor set a goal to double the number of trucks carrying soil to speed up the leveling but failed.

According to a representative of Cienco 1, because the site has not been cleared to have a road to carry materials, the company leased land from people from March 2021 to open a public service road, but the road is very small. Therefore, Cienco 1 recommends that the locality soon hand over the site to widen the road and increase the amount of transportation.

It is known that other bidding packages of the project are also accelerating the construction progress. The bidding package of Truong Son Construction Corporation also strives to open the route by the end of September 2022 at the request of Da Nang leaders.

Being reminded many times, the project of more than 1,000 billion VND in Da Nang

The western ring road project has a total investment of 1,500 billion VND. Photo: DB

Previously, the Inspectorate of Da Nang City announced the inspection conclusion of the implementation of the Western Ring Road project, pointing out many violations leading to the delay in progress.

Specifically, at the time of project formulation, the consultant only determined the impact of about 117 households, of which 95 households needed to be relocated and resettled, and only 5 hectares were prepared to arrange resettlement, so the project was established. does not propose to build resettlement areas. When implementing, there are 369 residential land records that need to be recovered, the number of land lots needed for resettlement is 625 and the land fund for resettlement around the project is not satisfied.

The Da Nang Traffic Construction Investment Project Management Board assessed and checked that the plan for site clearance and resettlement was not close to reality. advise the City People’s Committee to approve the project but does not show the plan for site clearance and resettlement.

The western ring road project has the starting point at National Highway 14B (Hoa Khuong commune, Hoa Vang district), the end point at Km 19+177.30 connecting the main road of the concentrated information technology park (Hoa Lien commune).

The total length of the whole route is 19.3km, started on September 14, 2018 and expected to be completed on October 29, 2020. The project has a total investment of 1,500 billion VND, in particular, phase 1 is more than 1,134 from the central budget and the Da Nang city budget.

The project is invested by the Construction Management Board of Da Nang traffic works, a consortium of contractors including Truong Son Construction Corporation and Cienco 1.