Close-up of Nam Cuong’s “trillion billion” project, leaving the grass growing after nearly 10 years of approval

Many times adjusting the schedule, Nam Cuong’s “trillion billion” project still leaves the grass to grow, despite the market’s scarcity of supply.

Close-up of the project "trillion"  of Nam Cuong removed the growing grass after nearly 10 years of approval - 1

Duong Noi new urban area of ​​Nam Cuong Group was approved by Ha Tay Provincial People’s Committee (old) for 6 years (from 2008 to 2013).

Close-up of the project "trillion"  of Nam Cuong removed the growing grass after nearly 10 years of approval - 3

However, the implementation process of the project was affected by the planning review for about 42 months (3.5 years), in 2014, the project was extended by Hanoi People’s Committee. Accordingly, the completion progress of technical infrastructure works will be completed before the fourth quarter of 2015, social infrastructure and other works will be completed by the fourth quarter of 2017.

Close-up of the project "trillion"  of Nam Cuong removed the growing grass after nearly 10 years of approval - 4

By 2018, the project will continue to be extended the implementation schedule. The implementation progress of the new urban area project will be completed before the fourth quarter of 2020. Technical and social infrastructure works must be handed over without compensation before the fourth quarter of 2019

Close-up of the project "trillion"  of Nam Cuong removed the growing grass after nearly 10 years of approval - 5

But after many renewals, until now, Duong Noi New Urban Area (Ha Dong District, Hanoi) still has many abandoned land lots, contrary to people’s expectations about the progress and completion of infrastructure projects. social class

Close-up of the project "trillion"  of Nam Cuong removed the growing grass after nearly 10 years of approval - 6

In June 2021, the Government Office sent a written request to the Ministry of Natural Resources and Environment, the Ministry of Natural Resources and Environment FinanceThe Ministry of Construction commented on the content of the report of the Hanoi People’s Committee on reviewing and clarifying the content of citizens’ accusations of land violations, construction and project implementation in Duong Noi ward (Ha Noi). Dong, Hanoi). Among them, there is the Duong Noi New Urban Area project of Nam Cuong Group Joint Stock Company

Close-up of the project "trillion"  of Nam Cuong removed the weeds after nearly 10 years of approval - 7

Also in this project, the Ministry of Natural Resources and Environment and the Ministry of Construction proposed to clarify whether the construction of substations in the planned land plots is green land and kindergarten land in accordance with the master plan. Has the construction detail of the 1/500 scale Duong Noi New Urban Area been approved?

Close-up of the project "trillion"  of Nam Cuong removed the growing grass after nearly 10 years of approval - 8

According to PV’s research, on December 26, 2007, Ha Tay Provincial People’s Committee (former) issued Decision No. 2568/QD-UBND, approving the detailed planning of 1/500 scale of Duong Noi New Urban Area. On July 2, 2008, Ha Tay Provincial People’s Committee issued Decision No. 1955/QD-UBND, adjusting the detailed planning of 1/500 scale of Duong Noi New Urban Area.

Close-up of the project "trillion"  of Nam Cuong removed the weeds after nearly 10 years of approval - 9

In the detailed adjusted land use planning table of Decision No. 1955/QD-UBND, section 5.1 shows the total number of villas is 2,253, the total number of adjacent houses is 544. However, in the planning map of 1/500 scale, with the stamp of the old Ha Tay Province Department of Construction, it shows the total number of villas is 2,716 units, the number of adjacent households is 592 units. Comparing these two figures, it can be seen that the planning map of 1/500 scale increases compared to Decision No. 1955/QD-UBND with 511 villas. In which, garden villas increased by 463 units, adjacent houses increased by 48 units

Traffic Newspaper will continue to inform!

According to Nguyen Hung (Traffic Newspaper)