Đầu Tư

The Ministry said the responsibility of Hanoi and Ho Chi Minh City

Hanoi urban railway project Nhon line – Hanoi station: Back to 2027-2029

Project by City People’s Committee. Hanoi decided to invest, project scale: the length of the route is 12.5 km (8.5 km overhead and 4.0 km underground). The project progress has reached 74.4% so far, it is expected to adjust the project completion schedule to December 2027. The project uses loans from the Asian Development Bank (ADB), the General Department of Treasury (DGT) of the French Government; The European Investment Bank (EIB) and the French Development Agency (AFD).

duong sat do thi 691
Hanoi urban railway project Nhon line – Hanoi station is flooded with progress, at least 2027-2029, new operation

According to the Ministry of Transport, the project has complex technology, which is applied for the first time in Vietnam; implementing units do not have practical experience. Bidding packages, in addition to complying with the laws of Vietnam, must also fully comply with the procedures prescribed by the sponsor, while the binding requirements under the Loan Agreement are different according to the suppliers. funding, so there are many problems when implementing.

In addition, the site clearance in the city. Hanoi faced many difficulties. The ground to deploy most of the construction on the main traffic routes of the city has a very large traffic volume, the organization of construction in the condition of the narrow ground, the partial handover of the site leads to the delay in progress. long.

The handling of letters and complaints of people during the implementation of the project is influenced by the policies of the donors.

The Ministry of Transport also considers that the capacity of investors/project management boards in managing projects with complex technologies and interwoven with multiple capital sources is still limited; The total project investment increased, the project implementation time was prolonged, leading to the need to carry out adjustment procedures.

duong sat do thi 692
Urban railway projects are still sprawling

Speaking of solutions, the ministry said: The Prime Minister has established a special working group, the City People’s Committee. Hanoi has established an interdisciplinary working group to review and remove difficulties and obstacles in order to promote the project progress. Currently, the parties focus on solving problems related to the difference between the FIDIC contract and the current Vietnamese law; problems related to regulations, standards, regulations on norms, unit prices – prices, prices of specialized materials and equipment Urban rail

Hanoi urban railway project Nam Thang Long – Tran Hung Dao line

Project by City People’s Committee. Hanoi decided to invest, the main scale: The total length of the route is 11.5 km (8.5 km underground, 3 km high) with 3 elevated stations, 7 underground stations. Loan from Japan Bank for International Cooperation. City budget counterpart capital. Hanoi.

The Ministry of Transport said the project “has the same problems as the Nhon-Hanoi Railway Station project”.

City People’s Committee Hanoi is completing procedures to adjust investment policies, expected to be completed in September 2022.

HCMC urban railway project Ben Thanh – Suoi Tien route

The project is invested by the People’s Committee of Ho Chi Minh City, project scale: Total length 19.7 km (2.6 km underground, 17.1 km high). The project implementation period is from 2007 to 2021, the progress of the project so far has reached 90.6%. It is expected that the construction completion time will be adjusted at the end of the fourth quarter of 2023. The project uses a loan from the Japan International Cooperation Agency (JICA, formerly JIBIC).

duong sat do thi 693
The project is waiting to adjust the implementation time.

The People’s Committee of Ho Chi Minh City is coordinating with the Ministry of Planning and Investment and the Ministry of Finance to submit to the Government to adjust the project implementation time and arrange to supplement all the unallocated medium-term ODA capital for 2021-2025. .

Ho Chi Minh City railway project on Ben Thanh – Tham Luong route

The project is invested by the People’s Committee of Ho Chi Minh City, main scale: Total length of 11,042 km (9,091 km underground, 1,951 km long) with 10 stations (9 underground stations, 1 elevated station) . The project uses loans from ADB, EIB, German Reconstruction Bank. The project implementation period is from 2011 to 2026, up to now, the construction of CP1 package “Construction of office buildings and ancillary works at Tham Luong Depot” has been completed, the remaining main packages of the project have been completed. The project is preparing to deploy contractor selection.

The People’s Committee of Ho Chi Minh City is completing the procedures to submit to the Ministry of Planning and Investment to adjust the disbursement time limit, speed up the site clearance to speed up the project progress and complete the policy adjustment procedures. investment, investment project.

Responsibilities of localities and of the Ministry of Transport

Urban railway projects are being implemented in Ho Chi Minh City. Hanoi and Ho Chi Minh City are both invested by the People’s Committees of these localities, assigning the project management boards under the city to be the investors and the specialized construction agencies under the City People’s Committee to appraise the documents. design.

Therefore, the Ministry of Transport affirmed that the entire direction and administration during the implementation of the projects is under the authority of the City People’s Committee. Hanoi and Ho Chi Minh City People’s Committee.

The Ministry of Transport said that it will continue to coordinate with the two cities, relevant ministries and branches to promptly solve and remove difficulties and obstacles, and support the People’s Committees of the two cities in the implementation process. put projects into operation and exploitation according to the set schedule.

Luong Bang

duong sat do thi nhon ga ha noi 2 468

Nhon urban railway – Hanoi station would like to delay the progress to 2029It is proposed to adjust the project implementation period from 2009-2022 to 2009-2029.
You are reading the article The Ministry said the responsibility of Hanoi and Ho Chi Minh City
at Blogtuan.info – Source: vietnamnet.vn – Read the original article here

Back to top button