Long Thanh International Airport project phase 1 is ahead of schedule

Tender package for the construction of pile foundation for the passenger terminal of the project Long Thanh International Airport completed earlier than expected. With the construction phase of bored piles, every day 250 workers and 32 drilling rigs and cranes are mobilized to the site.

For the package of ground leveling and drainage, so far the total volume of excavation and backfill has exceeded 2.8 million m3 compared to the plan. Complete leveling of the entire station core area.

In parallel with the construction work on the construction site, the technical design of the passenger terminal, runway, and apron was closely followed by the investor. The technical design document of the station body will be completed on June 18 for submission The transportation expertise.

Despite facing early rainy season climatic conditions, ACV, the project management board and construction units actively implemented scientific and flexible construction and initially exceeded the volume and controlled well. progress.

* Invite readers to watch programs broadcast by Vietnam Television on TV Online and VTVGo!

You are reading the article Long Thanh International Airport project phase 1 is ahead of schedule
at Blogtuan.info – Source: vtv.vn – Read the original article here

Back to top button