24 projects in Tuyen Lam lake national tourist area behind schedule

Recently, the Management Board of Tuyen Lam Lake National Tourist Area said that there are currently 24 projects in progress, most of which are behind schedule according to regulations. In addition, there are 3 other investment projects that have been withdrawn by Lam Dong Provincial People’s Committee.

After 18 years of operation, Tuyen Lam Lake National Tourist Area has a total of 37 investment projects granted investment certificates by the Provincial People’s Committee with a total initial capital of over 10,690 billion VND; in which, 13 projects have been completed and put into operation; 24 projects are in the process of being implemented, not yet put into business according to the issued investment certificates.

According to the Management Board of Tuyen Lam Lake National Tourist Area, there are currently 3 withdrawn investment projects: resorts, conferences – seminars, hotels of international standards of Dat Viet Joint Stock Company – VP; APU Cultural Village of Royal Saigon Da Lat Joint Stock Company.

Some units have been extended the progress of putting the land into use and adjusted the investment schedule; The remaining units are contacting the Department of Natural Resources and Environment and the Department of Planning and Investment for consideration and settlement according to regulations.

In addition, some investment units for the purpose of real estate business, do not comply with the objectives of tourism service business investment as the approved general plan of Tuyen Lam Lake National Tourist Area. . Some investors have weak financial potential, leading to a state of inactive project implementation.

In addition to the projects operating “moderately”, there are 13 projects of the units that have been put into operation with a total investment of about 2,500 billion VND, creating sightseeing, entertainment and tourism products. eco-tourism, adventure sports, resort with about 949 rooms… have brought positive socio-economic effects.

In addition to contributing revenues to the budget, the projects have provided about 1,200 jobs, attracting tourists to the resort…

According to the Management Board of Tuyen Lam Lake National Tourist Area, the cause of slow progress is the change when new laws are introduced (Law on Tourism, Law on Investment, Law on Construction, Law on Land, Law on Heritage). , Law on Forestry…);

The Government advocates to stop exploiting and exploiting forest products for natural forests by 2016), which affects the fact that investment projects cannot change land use purposes and exploit forest products to make full use of them.

At the same time, the procedure for approving the EIA report was previously done at the provincial level, according to the new law, it must be done at the Ministry of Natural Resources and Environment, and administrative procedures need a lot of time.

At the same time, the shared infrastructure of Tuyen Lam Lake National Tourist Area has not developed synchronously; there is no domestic water supply system to the project foot for investors, there are still some cases of ground clearance; wastewater treatment system has not been operated; waste collection system; the telecommunications system needs to be upgraded; The operating time of the public lighting system is limited…

https://cafef.vn/lam-dong-24-du-an-o-khu-du-lich-quoc-gia-ho-tuyen-lam-cham-tien-do-2022031723014618.chn


According to Minh Tam

You are reading the article 24 projects in Tuyen Lam lake national tourist area behind schedule
at Blogtuan.info – Source: cafebiz.vn – Read the original article here

Back to top button