Close the entrance of Vinh Tuy Bridge from Nguyen Khoai . Road

HanoiIn order to dismantle the two-span Vinh Tuy bridge in Hai Ba Trung district for phase 2 construction, the branch connecting Nguyen Khoai road to the bridge will be closed for about 3 months.

In the evening of March 26, the contractors erected a barricade, dividing traffic, serving for the demolition of the bridge and the construction and construction of the upper part of the T17HLA pillars to the T18HL pillars, belonging to the investment project stage of the Vinh Tuy bridge construction.paragraph 2.

The contractor’s representative said that a 2 span bridge was demolished, approximately 60 m long, in the direction of Hai Ba Trung – Long Bien.





The contractor arranged for the hardening of the Vinh Tuy bridge entrance from the Nguyen Khoai embankment on the evening of 26 March.  Photo: Van Hieu

The contractor arranged to close the entrance to the Vinh Tuy bridge from the Nguyen Khoai embankment from the evening of 26 March. Photo: Van Hieu

In order to service the demolition and construction of this item, the Hanoi Department of Transportation required a barrier of approximately 129 m from the bridge deck in the Hai Ba Trung district, and at the same time adjust the median between the bridges accordingly. The branch connecting Nguyen Khoai road to the Vinh Tuy bridge was also completely closed during the project construction period.

During the closing of the bridge entrance from Nguyen Khoai Road, trucks and passenger cars headed to Nguyen Khoai and Bach Dang roads and boarded the Thanh Tri bridge. At the same time, a temporary road under the bridge was also constructed to replace the Bach Dang road that passes through the project.

Motorcycles and cars are shared to go to Minh Khai Street and turn in front of the gates of the Times City urban area before taking the bridge to Long Bien.





Adjusted the dividing line between the bridges on the Hai Ba Trung district side to serve construction.  Photo: Van Hieu

Adjusted the dividing line between the bridges on the Hai Ba Trung district side to serve construction. Photo: Van Hieu

The Vinh Tuy 2 bridge construction project started in January 2021 with a total investment of more than 2,500 billion VND. This bridge has the same design as the Vinh Tuy 1 bridge with a total length and track of more than 3.4 km; cross section 19.25m (4 lanes); the static height of the bridge is 11m; The starting point is at Km0+840 (intersection with Nguyen Khoai and Minh Khai roads), the ending point is at Km4 + 312.62 (intersection with Long Bien – Thach Ban and Co Linh roads).

The Vinh Tuy 2 bridge is expected to be fully completed by June 2023, a synchronous connection with the overhead Ring 2 project is under construction, extending to the Nga Tu So junction.